HAVN Construction Update, October 2026: Tiling, Glazing and Sauna Fit-out
HAVN is in its building finishing stage. On 6 October 2026 the site team reported ceramic tiling being completed that week, glass for the gym and lobby scheduled for installation the following week, and timber work starting in the infrared sauna. Nineteen photographs were taken on site the same day and are published in the HAVN Gallery.
What stage is HAVN at in October 2026?
The structure and facade are complete, and wiring and interior finishing were completed in August. Since September the work has been building finishing: the surfaces, glazing, and fit-out that turn a completed structure into a usable building.
Walls along the corridors are rendered and painted. Many floors in the October photographs are still at screed level, which is where the ceramic tiling is being completed.
What work is happening on site this month?
The site team's report of 6 October 2026 lists three items. Each relates to a shared space or finish that residents will use every day.
- Ceramic tiling, scheduled to be completed in the week of 6 October.
- Glass for the gym and the lobby, scheduled for installation the following week.
- Timber work in the infrared sauna, starting in the week of 6 October.
What do the October photographs show?
The upper walkways run around the open centre of the building behind black steel balustrades, with residence doors along one side. On the ground floor the pool shell is formed and waiting for its finish. The concrete stair between the two levels is in place.
Inside, bathrooms show framed doorways and rough-in plumbing ahead of fit-out. The electrical metering and distribution boards are mounted. From the street, the two-storey facade is painted and the site entrance is still a working construction area.
How has construction progressed since February 2026?
HAVN has published construction photography every month since groundwork began. The stages below follow the monthly records in the Gallery.
| Month | Stage |
|---|---|
| February 2026 | Soil testing, pool excavation, and drilling |
| March 2026 | Foundations and steelwork |
| April 2026 | Foundations and structural columns |
| May 2026 | Second floor |
| June 2026 | General structural and finishing progress |
| July 2026 | Facade works and roofing |
| August 2026 | Wiring and interior finishing |
| September 2026 | Building finishing |
| October 2026 | Tiling, glazing, and sauna fit-out |
Where can you see every progress photograph?
The Development Progress view in the HAVN Gallery holds the full record, month by month, including all 19 photographs from 6 October. Each image is dated so it can be compared with the floor plans and the previous month.
Buyers who want to see the building in person can arrange a site visit. A virtual walkthrough is also available for buyers outside Bali.
Common questions
- Is HAVN still under construction?
- Yes. As of 6 October 2026 HAVN is in its building finishing stage, with ceramic tiling, gym and lobby glazing, and sauna timber work underway.
- What happens after building finishing?
- Each residence is delivered fully furnished and equipped, so the building works are followed by interior fit-out, furniture, and the installation of electronics and appliances.
- Where are HAVN's construction photographs published?
- In the Development Progress view of the HAVN Gallery at hetanny.com/gallery, organised by month from February 2026.
/6-October-Project-Progress-Building-Finishing-3.jpeg)
/01-July-Project-Progress (1).jpeg)
